The wave barge can receive each individual generator unit, installed one at a time on opposite sides to maintain the load balance.

Each arm is installed and mounted to the deck in (maintenance mode). The final components to be installed are the floats.

They should be installed after the raft is in place. As the floats are installed the wave generators are deployed to their operational positions.